The industrial weighing system should be designed based on the load transfer path, working conditions and its test method; Choosing a load cell is only one of the steps. If the load force does not pass through the sensor through a pipe, structure or other connection, even the right load cell and display will not necessarily show the true weight. Before buying the equipment, determine what will be weighed, in what condition and for what purpose.
Why is the weighing accuracy not only dependent on the characteristics of the load cell?
The load cell senses the change of the load applied to it; But the number that the operator sees is the result of the performance of the whole system: structure, mounting location, sensors, connections, display and calibration. OIML Recommendation R 60 also addresses the metrological requirements of the load cell separately from the requirements of the complete weighing instrument. Therefore, the good specification of a piece should not be equated with the confirmed performance of the set.
First write down the purpose of the measurement: inventory in the tank, amount passing through the line, weight of suspended load or weight of each load? Then inform the designer about the operating capacity, dead load of the structure, asymmetric loading, possible shocks and the required precision of the process. This information determines where the load should be transferred to the sensor and under what conditions the final test should be performed.
What design decision does each application change?
Weighing tanks: piping is also part of the problem
In the tank, the weight of the fluid or solid must pass through the supports equipped with the weighing module. A rigid connection of the pipes can force the tank and divert part of the weight change from the path of the sensor; The rigidity of the foundations and the restraint of the structure should also be checked. Before choosing the equipment, prepare a map of the foundations, inlet and outlet connections, a possible mixer and the state of the tank in empty and full state. Mettler Toledo's installation guide also emphasizes the effect of piping and the strength of the supports.
Conveyor: Don't hide a mechanical error by adjusting the display
The belt scale should measure the load on the belt along with its movement; This application is not the same as static tank weighing. Alignment of rollers, belt tension and distance from points such as loading and unloading place have an effect on the result. In the Siemens guide, it is recommended to check these factors and test reproducibility before modifying the settings based on the material test. To request a design, record the working speed, material flow range and the proposed installation location.
Crane: Weighing capacity is not a substitute for permitted lifting capacity
In suspended load weighing, in addition to measurement, the entire load bearing path is important: crane, scale, hook and load attachment equipment. None of them should be used beyond their authorized capacity. Before installation, check the mechanical compatibility of the equipment and the method of observing the weight by the operator; When working, the safety instructions are the same as the equipment.
Loader: Measure the weight of each bucket in working conditions
The loader weighing system is designed to record the weight of the load during the loading operation, not to replace an independent check of all machine limitations. When choosing, specify the car model, bucket type, load lifting method and the need to collect the loads of each truck. For example, the Tamtron product manual describes weighing materials as the bucket rises; Capabilities and operating conditions are dependent on the selected system and should not be generalized to all loaders.
Forklift: The sensing method changes the way the operator works
"Forklift weighing" is not the name of a single method. Some systems use a sensor assembly in the loader attachment, and some estimate weight indirectly from hydraulic pressure. In the pressure measurement method, the height of the probe, the position of the load, the friction and the lifting method can affect the result. Therefore, before buying, ask at what height and position the operator should weigh the load and how the system is installed and tested on your forklift model.
From site visit to delivery, what should we record?
You can take this checklist with you when making an inquiry or a technical visit:
summary
Before ordering, prepare a sheet including the type of equipment, capacity and working conditions, map or photo of the installation location, required output and delivery test criteria. Save this manual for the time of the technical visit; If the save option is enabled in Behzi account for you, you can keep it there. To ask questions about the project, send the specifications through the active communication channel on the mini-site of Touzin Saz Industries, owned by Mehdi Nazarinejad.